Construction Tips

🏗️ 5 Marla House Construction Material List & Cost in Pakistan (April 2026)

Planning to build a 5 Marla house in Pakistan? One of the first things you need is an accurate material list and cost estimate. In this complete April 2026 guide, we provide a detailed breakdown of all materials required for a standard 5 Marla house — from foundation to roof slab.


What is 5 Marla?

1 Marla = 272.25 Square Feet 5 Marla = 1,361 Square Feet

A standard 5 Marla house in Pakistan typically has:

  • Ground floor + First floor
  • 3-4 bedrooms
  • 2-3 bathrooms
  • Drawing room & kitchen

Phase 1 — Foundation Material List

MaterialQuantityPriceTotal Cost
Cement80-100 bagsCall for rate
Steel500-700 kgCall for rate
Crush Sargodha400-500 CFT₨ 185/CFT₨ 74,000-92,500
Sand Chenab200-300 CFT₨ 80/CFT₨ 16,000-24,000
Bricks2,000-3,000 nos₨ 27/nos₨ 54,000-81,000

Phase 2 — Grey Structure Material List

MaterialQuantityPriceTotal Cost
Cement350-450 bagsCall for rate
Steel1,500-2,000 kgCall for rate
Crush Sargodha600-800 CFT₨ 185/CFT₨ 111,000-148,000
Sand Chenab400-500 CFT₨ 80/CFT₨ 32,000-40,000
Bricks10,000-12,000 nos₨ 27/nos₨ 270,000-324,000

Phase 3 — Roof Slab Material List

MaterialQuantityPriceTotal Cost
Cement120-150 bagsCall for rate
Steel800-1,000 kgCall for rate
Crush Sargodha500-600 CFT₨ 185/CFT₨ 92,500-111,000
Sand Lawrencepur300-400 CFT₨ 220/CFT₨ 66,000-88,000

Complete Material Summary — 5 Marla House

MaterialTotal QuantityApprox Cost
Cement550-700 bagsCall for rate
Steel & Sariya2,800-3,700 kgCall for rate
A Grade Bricks12,000-15,000 nos₨ 324,000-405,000
Crush Sargodha1,500-1,900 CFT₨ 277,500-351,500
Sand Chenab600-800 CFT₨ 48,000-64,000
Sand Lawrencepur300-400 CFT₨ 66,000-88,000
Sand Ravi400-500 CFT₨ 26,000-32,500

Total Grey Structure Cost Estimate — 5 Marla

ItemEstimated Cost
Materials₨ 18-25 Lakh
Labour₨ 8-12 Lakh
Miscellaneous₨ 2-3 Lakh
Total Grey Structure₨ 28-40 Lakh

⚠️ Note: Costs are approximate and vary based on design, location, and material prices. Contact us for accurate estimate!


Money Saving Tips for 5 Marla House

Buy all materials from one supplier — saves transport cost ✅ Order in bulk — get better rates ✅ Plan properly before starting — avoid wastage ✅ Use A Grade materials — saves repair costs later ✅ Get multiple quotes before hiring contractor ✅ Supervise daily — avoid material theft


Common Mistakes to Avoid

❌ Reducing cement ratio to save money ❌ Using B Grade bricks for load bearing walls ❌ Buying cheap steel to cut costs ❌ Not hiring qualified engineer ❌ Starting construction without proper plan ❌ Buying materials without comparing prices


Why Buy from Material Provider?

At Material Provider Pakistan, we supply all materials for your 5 Marla house:

  • ✅ Crush & Aggregate — All types
  • ✅ Sand — Lawrencepur, Chenab, Ravi
  • ✅ Bricks — A Grade, B Grade
  • ✅ Cement — All top brands
  • ✅ Steel — All major brands
  • ✅ One stop solution for all materials
  • ✅ Fast delivery across Lahore & Pakistan
  • ✅ Bulk order discounts
  • ✅ Free consultation on material quantities

📞 Get Free Material Estimate

Planning to build? Contact us for free material quantity estimate:

📞 0321-4444537 💬 WhatsApp: 0321-4444537 🌐 materialprovider.com 📍 Lahore, Pakistan


⚠️ Disclaimer: All quantities and costs are approximate for a standard 5 Marla house. Actual requirements may vary based on design and specifications. Prices are as of April 2026.

Leave a Reply